UPS Cargo Terminal Project

  • *Project Timeframe: May 2020 – Ongoing
  • *Project Subject: Fabrication and installation of all mechanical systems works are carrying out.
  • *Scope of the Work: 5.5 km long conveyor line, 52 teloscopic conveyors, 202 cargo transfer vehicle capacity metro line, transfer center with an hourly capacity of 16.000 packages.
  • *Project Owner: UPS Cargo
  • *Prime Contractor: Berrmak
  • *Companies work with: Oskon,Serka,İss,İndata,Asc
  • *#of Employees Working in the Project: 50+
  • *Lost Days because of Work Injury: 0
  • *Total Project Area / Worked Project Area: 55.000 m2 / 31.000 m2